Commissioner Dr. Joseph P. Scarpelli, would like to notify residents of an upcoming PSE&G roadway project in Nutley that may impact Township residents. This notification is sent to inform residents of the upcoming work so that alternate routes can be planned if needed and to maintain a level of safety within the community.
Starting Thursday, September 19, 2024, and continuing through the beginning of October 2024, PSE&G will be milling and repaving the below roadways as part of their gas main upgrade project. The work will occur between the hours of 7 AM to 5 PM and will be contingent on weather conditions.
The contractor performing the roadway work for PSE&G is Tilcon New York, LLC.
If you have any questions, please reach out to PSE&G directly on their project hotline at 1-833-661-6300. If you are unable to contact PSE&G, feel free to contact my office at 973-284-4958.
Roadways impacted by PSE&G Gas Main Upgrade Project
STREET NAME | BETWEEN SECTION 1 | BETWEEN SECTION 2 | MILLING DATE | PAVING DATE |
DARLING AVENUE | Kingsland St | High Street | 9/19 | 9/25/2024 |
RENNER AVE | High St | Reigate Rd | 9/19 | 9/25/2024 |
RHODA AVE | High St | Norman St | 9/19 | 9/25/2024 |
JOERG AVE | High St | Kingsland St | 9/19 | 9/25/2024 |
CADMUS ST | Darling Ave | Joerg Ave | 9/20 | 9/25/2024 |
CHARLES ST | Darling Ave | Joerg Ave | 9/20 | 9/25/2024 |
JOERG AVE | Kingsland St | Cul-De-Sac | 9/20 | 9/26/2024 |
KENZEL AVE | Kingsland St | Cul-De-Sac | 9/20 | 9/26/2024 |
KENZEL AVE | Kingsland St | High Street | 9/23 | 9/26/2024 |
MAPES AVE | High St | Norman St | 9/23 | 9/26/2024 |
STANLEY AVE | High St | Norman St | 9/23 | 9/27/2024 |
NORMAN ST | Rhoda Ave | Stanley Ave | 9/24 | 9/27/2024 |
ALEXANDER AVE | High St | Kingsland St | 9/24 | 9/27/2024 |
WINDSOR PL | Kingsland St | 85' North | 9/24 | 9/27/2024 |
OAKLEY TER | Kingsland St | Cul-De-Sac | 9/24 | 9/27/2024 |
OAKLEY TER | Oakley Ter | Edison Ave | 9/25 | 9/30/2024 |
EDISON AVE | Kingsland St | High St | 9/25 | 9/30/2024 |
SPRUCE ST | Edison Ave | Funston Pl | 9/25 | 9/30/2024 |
EMILY AVE | Edison Ave | Bloomfield Ave | 9/26 | 9/30/2024 |
LAURA AVE | Edison Ave | Bloomfield Ave | 9/26 | 9/30/2024 |
BLOOMFIELD AVE | Kingsland St | High St | 9/26 & 9/27 | 10/1/2024 |
FUNSTON PL | Spruce St | High St | 9/27 | 10/1/2024 |
GLENDALE ST | Franklin Ave | Passaic Ave | 9/27 | 10/1/2024 |
PASSAIC AVENUE | Baltimore St | End of patches | 9/27 | 10/1/2024 |
HARRISON ST | Brookline Ave | Evergreen Ave | 9/27 | 10/1/2024 |